| | An Assessment of the Effects of the Ontario Hydro Redevelopment Project |
 | | It diverted water from the Grass Island Pool, near Chippawa, Ontario, through a more than 20 kilometre (12 mile) long open-cut canal, to the crest of the Niagara Gorge near Queenston, Ontario. |
 | | According to the Commission's Order of Approval of August 15, 1961, construction of the works was to be carried out under the general supervision of the Commission and the five additional sluices were to be operated under the control and supervision of the International Niagara Board of Control. |
 | | On April 8, 1963, the Power Authority of the State of New York applied to the Commission, with the support of the Hydro-Electric Power Commission of Ontario, through the Governments of Canada and the United States, for approval to reduce the elevation of a shoal in the Niagara River. |