 | | This will increase Garyville's refining capacity from 245,000 bpd to 425,000 bpd and Marathon's total refining capacity from 974,000 bpd to 1,154,000 bpd. |
 | | In addition to the installation of a new crude and vacuum distillation unit, expansion plans call for the construction of infrastructure and other process units with the following design capacities: a 44,000 bpd delayed coker, a 70,000 bpd heavy gas oil hydrocracker, a 65,000 bpd reformer and a 47,000 bpd kerosene hydrotreater. |
 | | Some factors that could cause the actual results to be different than expected include necessary regulatory and third-party approvals, crude oil supply and transportation logistics, availability of materials and labor, unforeseen hazards such as weather conditions, and other risks customarily associated with construction projects. |