| | Kiantone Pipeline Corp - Decision March 22, 1994 (Site not responding. Last check: 2007-11-06) |
 | | The Department Staff, on November 22, 1993, consented to the proposed reroute along the Point Peter Road right-of-way, provided that Allen Springs Brook either be crossed in the dry or by pumping the stream flow around the work area. |
 | | On February 22, 1994, the Department Staff transmitted a "final" draft permit to the parties and requested clarification from the Applicant regarding two items in the KPC February 4, 1994 letter. |
 | | On March 7, 1994, I received from the Department Staff the draft permit and a letter requesting the matter be remanded to Staff for final processing and permit issuance, if I, and subsequently the Commissioner, found all issues to be satisfactorily resolved. |