 | | When the subbase material is too coarse (more than 20% retained on the 3/4-inch sieve) to use these methods or when No. OGS material is used, compaction will be determined based on nonmovement of the material under the compaction equipment. |
 | | Where subbase is 1/2-inch or more deficient from the depth indicated, scarify to a 3-inch depth, blend with additional material, recompact, or otherwise correct, as directed. |
 | | However, payment may be made to 75% of the quantity of the subbase on current estimates, in advance of the succeeding operations, provided the subbase has been satisfactorily completed and maintained, pending placement of the base course or pavement. |