| | YVR (Vancouver International Airport) Domestic Upgrade - Welcome to Read Jones Christoffersen: Innovative Structural ... (Site not responding. Last check: 2007-11-07) |
 | | Vancouver International Airport's Domestic Terminal, which was originally built in 1968, needed a complete seismic upgrade as well as improvements and updates to all types of aesthetic, service, and baggage handling systems. |
 | | But, as representatives of the Vancouver Airport Authority stressed to RJC, the airport, which handles both scheduled domestic and charter airlines, had to remain operational throughout and disruption to its users minimized. |
 | | Through the plan, the Airport Authority was able to schedule the seismic work, which was also phased over a 20-year period to satisfy cash-flow requirements for whenever an opportunity, such as tenant relocation, arose. |
| www.rjc.ca /cms/page2615.cfm (401 words) |
|