| | Water Technology - Crystal Project, Douglas Water Treatment Plant (WTP) |
 | | The Isle of Man Water Authority is responsible for collecting, treating and distributing some 10,000 million litres of water — around 26 million litres of water per day in the winter and approaching 35 million in the summer — to 31,000 connections over an area of 250 square miles. |
 | | However, later studies subsequently led to a revision — the design horizon was reset to 2021 and the projection population accordingly adjusted to 90,000, with parallel modification of the daily per capita usage from 150l in 2016, to an anticipated 185l by 2021. |
 | | Construction began on the raw water and treated water lines in January and June 2006, respectively; the former was completed in August and the latter will be finished in December. |